William B. Walton, et al. v. Neskowin Regional Sanitary Authority

Paid petition · Supreme Court of Oregon, No. S069004 · judgment May 23, 2024


Certiorari denied · January 27, 2025
Pre-decision estimate: 1% cert probability

Before the decision, well below the 4.1% base rate, with no standout signals pointing toward a grant.

Question presented

In the mid-1990s the Neskowin Regional Sanitary Authority (Sanitary Authority) and the Walton Family entered into a purported agreement that allowed the Sanitary Authority to bury a sewer line on the Walton’s property in exchange for a free sewer hook-up when needed. The sewer line was then installed and remained on the Walton’s property for years without incident. In 2015, however, the Sanitary Authority required the Walton Family to officially hook-up to its sewer system. The Walton Family sought their free hook-up, which the Sanitary Authority summarily refused. The Waltons filed a state takings lawsuit, claiming the Sanitary Authority’s refusal to grant their free hook-up, while maintaining a physical sewer line on their property effected an unconstitutional taking without compensation. The state circuit court dismissed the Walton’s takings claim under Oregon’s statute of limitations, stating the Waltons should have brought their takings claim back when the Sanitary Authority first installed its sewer line. The Oregon appellate and supreme court affirmed. The question presented is: Whether a Constitutional Fifth Amendment Takings Claim, based on a physical occupation, fully accrues and the statute of limitations begins to run before the government refuses to provide just compensation.

Counsel of record

For petitioner
James J. Walton

For respondent
Christopher Thomas Griffith
Haglund Kelley LLP

Case

Conference history
Distributed for 1 conference

Linked docket
24A58

Proceedings

  1. Jan 27 2025
    Petition DENIED.
  2. Jan 08 2025
    DISTRIBUTED for Conference of 1/24/2025.
  3. Dec 23 2024
    Waiver of right of respondent Neskowin Regional Sanitary Authority to respond filed.
  4. Nov 12 2024
    Motion to extend the time to file a response is granted and the time is extended to and including December 30, 2024. See Rule 30.1.
  5. Nov 08 2024
    Motion to extend the time to file a response from November 29, 2024 to December 29, 2024, submitted to The Clerk.
  6. Oct 16 2024
    Petition for a writ of certiorari filed. (Response due November 29, 2024)
  7. Jul 18 2024
    Application (24A58) granted by Justice Kagan extending the time to file until October 18, 2024.
  8. Jul 15 2024
    Application (24A58) to extend the time to file a petition for a writ of certiorari from August 21, 2024 to October 18, 2024, submitted to Justice Kagan.