Supreme Court Report

Supreme Court of the United States · Official docket →

FirstEnergy Service Company v. Federal Energy Regulatory Commission, et al.

Paid petition · United States Court of Appeals for the Sixth Circuit, No. 21-4072, 22-3351, 23-3324, 23-3366, 23-3417 · judgment January 17, 2025


Certiorari denied · November 10, 2025
Pre-decision estimate: 2% cert probability

Before the decision, well below the 4.1% base rate, with no standout signals pointing toward a grant.

Questions presented

  1. Whether a federal agency does not act arbitrarily or capriciously in determining that a postsettlement change of law concerning one alleged component of a settlement does not warrant unwinding the settlement.

  2. Whether a federal statute stating that the Federal Energy Regulatory Commission “shall . . . provide for incentives to each transmitting utility or electric utility that joins a Transmission Organization,” 16 U.S.C. § 824s(c), applies regardless whether the utility joined a Transmission Organization voluntarily or pursuant to a state-law mandate.

  3. Whether federal law preempts a state law mandating that a utility owning transmission assets within the state join a Transmission Organization. (i)

Counsel of record

For petitioner
Sanford Ian Weisburst
Quinn Emanuel Urquhart & Sullivan, LLP

For respondent
Cynthia S. Bogorad
Spiegel & McDiarmid, LLP

Case

Conference history
Distributed for 1 conference

Amicus briefs
2 cert-stage

Related
Vide, 24-1318

Proceedings

  1. Nov 10 2025
    Petition DENIED. Justice Alito took no part in the consideration or decision of this petition.
  2. Oct 08 2025
    DISTRIBUTED for Conference of 11/7/2025.
  3. Oct 03 2025
    Reply of petitioner FirstEnergy Service Company filed.
  4. Sep 22 2025
    Brief of respondent Office of the Ohio Consumers' Counsel in opposition filed. VIDED.
  5. Sep 22 2025
    Brief of Federal Respondent in opposition filed. VIDED.
  6. Sep 19 2025
    Brief of respondent Public Utilities Commission of Ohio in opposition filed. VIDED.
  7. Jul 24 2025
    Brief of respondent PJM Interconnection, L.L.C. in support filed. VIDED.
  8. Jul 24 2025
    Brief amicus curiae of Edison Electric Institute (July 25, 2025 - to be corrected PDF and booklet)
  9. Jul 24 2025
    Brief amicus curiae of Edison Electric Institute filed (July 28, 2025 - Corrected).
  10. Jul 17 2025
    Motion of Buckeye Power, Inc. to extend the time to file a response from July 24, 2025 to September 22, 2025, submitted to The Clerk.
  11. Jul 17 2025
    The motions to extend the time to file responses are granted and the time is extended to and including September 22, 2025, for all respondents.
  12. Jul 17 2025
    Brief of respondent Duke Energy Ohio, Inc. in support filed. VIDED.
  13. Jul 16 2025
    Motion to extend the time to file a response is granted and the time is extended to and including August 25, 2025.
  14. Jul 16 2025
    Motion of Office of the Ohio Consumers' Counsel to extend the time to file a response from July 24, 2025 to September 22, 2025, submitted to The Clerk.
  15. Jul 16 2025
    Motion of Public Utilities Commission of Ohio to extend the time to file a response from July 24, 2025 to September 22, 2025, submitted to The Clerk.
  16. Jul 15 2025
    Motion to extend the time to file a response from July 24, 2025 to August 25, 2025, submitted to The Clerk.
  17. Jun 20 2025
    Petition for a writ of certiorari filed. (Response due July 24, 2025)