Supreme Court Report

Supreme Court of the United States · Official docket →

Electric Power Supply Association v. Federal Energy Regulatory Commission, et al.

Paid petition · United States Court of Appeals for the District of Columbia Circuit, No. 21-1214, 21-1216, 21-1217, 22-1063, 22-1065, 22-1066 · judgment August 15, 2023


Certiorari denied · May 28, 2024
Pre-decision estimate: 13% cert probability (95% interval 9%–20%)

Before the decision, about 3.2× the 4.1% base rate. The model weighted this up for counsel who has won certiorari before, a D.C. Circuit decision below, and a circuit split argued in the petition.

Question presented

The Federal Power Act, 16 U.S.C. § 824 et seq, establishes the framework for federal regulation of the electric power industry. Its fundamental premise is that, in exchange for enormously costly infrastructure investments to supply a public good, public utilities like generators retain the right to set their rates in the first instance, subject to reversal by the Federal Energy Regulatory Commission (FERC) only where those rates are unjust, unreasonable, or unduly discriminatory. Since the advent of regulatory reforms in the late 1990s and early 2000s, much of the electric grid in this country is now governed by sub-regulatory Regional Transmission Organizations and Independent System Operators, which—with oversight from FERC— largely set prices for wholesale electricity products via auctions. The question presented is whether a public utility supplier’s offer into such an auction structure, whereby it offers to provide a given electricity product at or above a specified price, is a “rate[] * * * demanded” under Section 205 of the Federal Power Act (16 U.S.C. § 824d(a)), and therefore may be set aside only by FERC (and not dictated by non-governmental third parties), and then only upon a finding that it is unjust, unreasonable, or unduly discriminatory.

Counsel of record

For petitioner
Paul Whitfield Hughes
McDermott Will & Emery

For respondent
Elizabeth B. Prelogar
Solicitor General

Case

Conference history
Distributed for 1 conference

Linked docket
23A403

Proceedings

  1. May 28 2024
    Petition DENIED.
  2. May 07 2024
    DISTRIBUTED for Conference of 5/23/2024.
  3. May 06 2024
    Reply of petitioner Electric Power Supply Association filed. (Distributed)
  4. Apr 17 2024
    Brief of Federal Respondent in opposition filed.
  5. Mar 18 2024
    Motion to extend the time to file a response is granted and the time is further extended to and including April 17, 2024.
  6. Mar 15 2024
    Motion to extend the time to file a response from March 18, 2024 to April 17, 2024, submitted to The Clerk.
  7. Feb 16 2024
    Brief of respondent Constellation Energy Generation, LLC in support filed.
  8. Jan 26 2024
    Motion to extend the time to file a response is granted and the time is extended to and including March 18, 2024, for all respondents.
  9. Jan 25 2024
    Motion to extend the time to file a response from February 16, 2024 to March 18, 2024, submitted to The Clerk.
  10. Jan 12 2024
    Petition for a writ of certiorari filed. (Response due February 16, 2024)
  11. Nov 03 2023
    Application (23A403) granted by The Chief Justice extending the time to file until January 12, 2024.
  12. Nov 01 2023
    Application (23A403) to extend the time to file a petition for a writ of certiorari from November 13, 2023 to January 12, 2024, submitted to The Chief Justice.