Centennial Resource Production, LLC v. Northern Natural Gas Company

Paid petition · Supreme Court of Nebraska, No. S-23-647 · judgment March 29, 2024


Certiorari denied · October 7, 2024
Pre-decision estimate: 4% cert probability

Before the decision, roughly the 4.1% base rate. The model weighted this up for a petition filed soon after the judgment below, a business petitioner, and counsel who has filed here before, and down for a business respondent.

Question presented

The question presented in this case involves a constitutional issue of first impression under the Due Process Clause of the 14th Amendment: Whether the exercise of personal jurisdiction by a state court, over a non-resident defendant, based exclusively on actions taken by the non-resident in compliance with a federal regulatory requirement, violates the constitutional due process standards set forth by this Court under the 14th Amendment, which require that a non-resident must have purposefully availed itself of the privilege of engaging in business within the state. (i)

Counsel of record

For petitioner
William F. Demarest Jr.

For respondent
Patrick Steven Cooper
lnserra | Kelley | Cooper | Sewell

Case

Subject area
Due Process (estimated from the questions presented, in the Supreme Court Database’s categories)

Conference history
Distributed for 1 conference

Order
Order list, October 7, 2024 · Certiorari denied

Proceedings

  1. Oct 07 2024
    Petition DENIED.
  2. Jul 17 2024
    DISTRIBUTED for Conference of 9/30/2024.
  3. Jul 15 2024
    Waiver of right of respondent Northern Natural Gas Company to respond filed.
  4. Jun 18 2024
    Petition for a writ of certiorari filed. (Response due July 22, 2024)